Checking in with the Indiana project…really I don’t check in, I should actually pitch a tent out back because I’m there so much.
This week there are different sub-contractors running all over the house. Â The HVAC will be roughed in and should be complete by the end of the week. This was a significant unforeseen expense. The house has an existing oil furnace and we are changing it over to natural gas, this required all new equipment. Â We knew that we had to extend central a/c to the upstairs but we had no idea that we would upgrade the entire system and switch fuel types. This was a blow to the budget and we had to make some adjustments.
Plumbers will begin their work this week. Â The plumbing rough-in is expected to be complete by the end of this week. I spent most of last Friday afternoon learning about drop-in acrylic tubs and doing some price comparison.
Electrical rough-in is almost complete, the absence of a concrete kitchen plan has delayed the electrician’s work.
The windows were measured last week. The window installation is now 3-4 weeks away, this will result in the largest delay in the project thus far. I cannot move on to the next level until the entire rough-in and framing are inspected and the house cannot be inspected unless the new windows are in.
This week the carpenter will continue to repair the exterior. Some of the shakes needed to be replaced or added where windows were deleted. When the vinyl siding was installed all of the molding around the windows was trimmed down and the original wood brackets were also cut. Â All of those are being repaired to look as they did when the house was built.
Thanks for playing,